VBHC Haven of Joy construction status as of 14 Oct 2024:
Structural works
B1 Wing:
RCC Structural work has been completed up to 16th floor & 17th floor WIP for 102, 103, 104, 105, 106, 107, 108, 109 series. RCC work completed to 15th floor & 16th floor WIP for 101 &110 series
B2 Wing:
RCC Structural work has been completed up to 15th floor and 16th floor WIP for all series.
B3 Wing:
RCC Structural work has been completed up to 15th floor and 16th floor WIP for all series.
B4 Wing:
RCC Structural work: 101 & 102 flat series is completed up to 15th floor and 16th floor WIP. 103 & 104 series flat completed up to 14th floor and 15th floor WIP.
Finishing works
B1 Wing:
Waterproofing works is done up to 10th floor & 11th floor WIP and Tiling works is done up to 9th floor &10th floor WIP. Putty works is done up to 10th floor &11th floor WIP. Balcony railing works are done up to 14th floor. Door frame installation works is completed up to 14th floor& 15th floor WIP.
B2 Wing:
Waterproofing works is done up to 9th floor & 10th floor WIP and Tiling works is done up to 8th floor & 9th floor WIP. Putty works is done up to 8th floor & 9th floor WIP. Balcony railing works are done up to 13th floor& 14th floor WIP. Door frame installation works is completed up to 13th floor & 14th floor WIP.
B3 Wing:
Waterproofing works is done up to 8th floor & 9th floor WIP and Tiling works is done up to 8th floor &9th floor WIP. Putty works is done up to 9th floor & 10th floor WIP. Balcony railing works are done up to 6th floor& 7th floor WIP. Door frame installation works is completed up to 13th floor& 14th floor WIP.
B4 Wing:
Waterproofing works is done up to 8th floor & 9th floor WIP and Tiling works is done up to 8th floor &9th floor WIP. Putty works is done up to 8th floor & 9th floor WIP. Balcony railing works are done up to 10th floor& 11th floor WIP. Door frame installation works is completed up to 12th floor& 13th floor WIP.
Finishing Activities:
Putty and Tiling works in Flats & Corridor Painting works
UPVC window fixing and Balcony railing work
All project information and details displayed on the site, including but not limited to the information and details contained in project related materials that you may download are for information purposes only and do not constitute an offer under any law for the time being in force. The Company shall not be liable to you for any decisions you may take as a result of or on the basis of such information and encourages you to contact the Company directly for up-to-date and accurate information.
The imagery used on the website and brochures are indicative only. Photographs of interiors, surrounding views and location may have been digitally enhanced or altered and do not represent actual views or surrounding views. These photographs are indicative only.
Changes may be made during the development of a real estate project and standard fittings and specifications are subject to change without notice. Standard fittings and finishes are subject to availability and vendor discretion. Fittings, finishes and fixtures shown in the images contained in this brochure are not standard and will not be provided as part of an apartment. The information contained herein is believed to be correct but is not guaranteed. Prospective purchasers should make and must rely on their own enquiries. The colors of the buildings are indicative only. This website and all brochures are a guide only and do not constitute an offer or contract.
Disclaimer: The images used on the website and brochures are indicative only. Photographs of interiors, surrounding views and location may have been digitally enhanced or altered and do not represent actual views or surrounding views. These photographs are indicative only.